Roading improvements

  • Project typeRoading
  • Project schedule2024 - 2026
Aerial photo of Port Road bridge.

Find out about roading improvement projects that have been scheduled, including:

  • safety improvements
  • new footpaths and cycle paths
  • pavement construction
  • seal extensions
  • resealing
  • bridge repairs.

To view roading projects in a map format follow the link below.

Roading improvements and renewal programme GIS map

Below is an overview of the work scheduled within the Roading improvements and renewals programme, grouped by the year the construction is expected to start. 

This list was last updated on 10 October 2025. 

2025 overview

The following are expected to start construction in 2025. 

Location and overview Expected start Status
Central Avenue - new footpath July 2025 Complete (physical works)
Gillingham Road - Bridge upgrade - new bridge July 2025 Construction underway
Springsflat and SH 1 - new roundabout July 2025 Construction underway
Nova Scotia Drive - Bridge No. 102 - structure component replacement August 2025 Procurement (physical works)
Wairahi Road - drainage August 2025 Construction underway
Wairahi Road - kerb and channel August 2025 Construction underway
Mains Avenue / Cairnfield Road - intersection improvements - safety September 2025 Construction underway

Kamo Road - rail overbridge strengthening - structure component replacement

October 2025 Procurement (physical works)
McLean Road - seal extension October 2025 Construction underway
Tikipunga Falls - new footpath and caravan dump station October 2025 Procurement (physical works)

Gray Road - seal extension

October 2025 Procurement (physical works)
Jordon Valley Road - sealed road pavement rehabilitation November 2025 Procurement (physical works)
Ormandy Road - RP 4791 - 6791 (2.0km) - seal extension November 2025 Procurement (physical works)
Pacific Bay Road - sealed road pavement rehabilitation November 2025 Procurement (physical works)
Paparoa Road - sealed road pavement rehabilitation November 2025 Procurement (physical works)
Pipiwai Road - shape correction and guardrail Noveber 2025 Procurement (physical works)
Waiotira Road - sealed road pavement rehabilitation November 2025

Procurement (physical works)

Whareora Road - sealed road pavement rehabilitation November 2025 Procurement (physical works)
Wharf Road - share correction and guardrail November 2025 Procurement (physical works)
Hikurangi - footpath renewal December 2025 Planning
Kotata Rise - safety improvement - linemarking and guardrail new safe crossing point path and drainage December 2025 Procurement (physical works)
Parua Bay Village - new footpaths and safety improvements December 2025 Procurement (physical works)
Reotahi - slip repair December 2025 Design
Bay View Road - RP 359 - slip repair (underslip) Complete Construction underway
Kaiikanui Road - RP 10153 - slip repair Complete Complete (physical works)
Karaka Road - RP 4990 - slip repair Complete Complete (physical works)y
Waipu Caves Road - Bridge No. 106b  - structure component replacement Complete Construction underway

2026 overview

The following are expected to start construction in 2026. 

Location and overview Expected start Status
Kioreroa Road - sealed road pavement rehabilitation January 2026 Procurement (physical works)
Marsden Bay Drive - sealed road pavement rehabilitation January 2026 Procurement (physical works)
Millbrook Road - McAulleys Bridge 78B - deck replacement January 2026 Design
Onerahi Road / Old Onerahi Road - pedestrian and cyclist safety improvements January 2026 Procurement (physical works)
Pataua North Road - sealed road pavement rehabilitation January 2026 Procurement (physical works)
Peach Orchard box culvert - bridge renewal January 2026

Design

Pipiwai Road - slip repair January 2026 Design
Rosythe Road - box culvert - structure component replacement January 2026 Design
Valley View Road - sealed road pavement rehabilitation January 2026 Procurement (physical works)
Kauika Road - Bridge B15 - structure component replacement February 2026 Design
Kopipi Crescent, Ngunguru - new footpath (linking playground, sports park etc.) February 2026 Procurement (physical works)
Mill Road and Whareora road - guardrail February 2026 Procurement (physical works)
Reyburn Street Bridge - structure component replacement February 2026 Design
Whangarei Heads - culvert replacement and slip remediation February 2026 Design
Corks Road - new footpath March 2026 Procurement (physical works)
Ohawini - concrete boat ramp construction and causeway repairs March 2026 Design
Pataua North - seawall extension March 2026 Planning
Punaruku - culvert replacement / road raising March 2026 Planning

2027 overview

The following are expected to start construction in 2027. 

Location and overview Expected start Status
Pataua - footbridge replacement (investigation only) March 2027 Planning
Riverside Drive - new signalised pedestrian crossing 2026 / 2027 Design
Te Mika - intersection improvements 2026 / 2027 Design
Whau Valley - signalised pedestrian crossing 2026 / 2027 Design

2027 / 2028 overview

The following are expected to start construction in either 2027 or 2028. 

Location and overview Expected start Status
Kamo Village - new signalised pedestrian crossing 2027 / 2028 On hold
Moody Avenue - safety improvements April 2026 Design
Ngunguru Road / Sands Road - design of new roundabout 2027 / 2028 Design
Weir Crescent - new footpath 2027 / 2028 Procurement (physical works)

To be confirmed

The construction start dates for the following are to be confirmed.

Location and overview Expected start Status
Snooks Road - RP 7240 - slip repair To be confirmed On hold

Our roading projects align with what we say we will do in our Long Term and Annual Plans, and are funded jointly from your property rates and Waka Kotahi.

The 2024 Government Policy Statement (GPS), which covers funding for our roading programme, indicated that no subsidy funding would be made available for council seal-extension projects on local roads for the 2024 - 2027 period.

Also, in our Long Term Plan 2024-2034, we have made no additional budget provision for Council-funded seal-extension projects on local roads. Therefore, no new seal-extension projects are planned on Council roads for the 2024 - 2027 period.

General Circular Investment: No 16 / 04 – Changes to the investment assessment process for the Roading Maintenance and Operations Activity Class (nzta.govt.nz)