We have good news to share this week. For the first time, we can see a clear path to reopening Russell Road in October 2026, provided the weather cooperates and there are no further ground stability issues.
This is the news we've all been waiting to hear, and we know the local community will welcome an earlier projected reopening date.
The reopening will come with a few caveats however: The road will still be subject to trigger and response plans relating to the unstable ground at the top of the slip site and, if the site receives heavy rainfall, we may need to close it for safety reasons. We may return in the future to remove the last of the earth from the top of the slip site once the ground has dried and settled, noting it is not expected to result in future road closures. However, even with these caveats, it's positive news.
All Moxy trucks have now left the site, and we have removed the road barriers between the fill site and slip site during two night-work sessions on 17 and 18 September 2026. Special thanks again to the residents on Russell Road for their cooperation and patience while we completed this work.
This week, we've completed the final drainage works at the slip site, including installing large manholes ahead of the Euroflo pipe installation, which is now underway. The Euroflo pipe is 400mm in internal diameter and will enable water to flow from the upper slip area down to the culvert under the road.
We have also completed the final tidy up of the forestry track and associated swales, and we've completed road-level drainage works, as well as the slip-side subsoil drainage. We've completed the hydroseeding on the small haul road slip and at fill site 1A and partially completed the hydroseeding on the main slip upper area.
Road surface rehabilitation is now underway, with our road pavement crew establishing onsite on Monday 21 September 2026. The work will include improving the subgrade layers and reshaping damaged sections of road before the basecourse and surfacing are completed in the coming weeks.
We will continue to base progress on key milestones and will update our progress weekly.
Here are the key points of interest from the past week:
- Russell Road is on track to reopen in October 2026, if weather conditions remain favourable and we encounter no further ground stability issues.
- Moxy trucks have all left the work site.
- Road barriers between the fill site and slip site have been removed.
- We have installed large manholes in preparation for the Euroflo pipes.
- Pavement crews are establishing onsite today (Monday 21 September 2026).
- Kaiikanui Road pilot vehicles escorted a total of 1,877 vehicles in the week ending 17 September 2026, with pilots running 6:30am to 6:30pm.
Aerial view of the Russell Road slip taken 15 September 2026, showing some of the drainage being constructed at road level.