Construction starts on wastewater capacity increase
Published on 17 November 2026
Council members and officers, contractors and representatives from Patuharakeke at the construction site blessing.
We are unlocking additional wastewater capacity for Bream Bay homes and businesses with construction starting on a new interim wastewater solution this week.
Creation of a new discharge area is now underway, located just north of the existing Ruakākā Wastewater Treatment Plant, at Poupouwhenua Reserve.
The new discharge pipe network will be connected to the existing treatment plant, increasing the available discharge capacity and allowing development in the area to pick up momentum again after being constrained by the existing discharge limits.
Manager – Wastewater Simon Charles describes it as a pragmatic step to help manage growth while carefully managing environmental impacts.
“Contractors will start by preparing site access and undertaking some vegetation removal. This work is being done in partnership with ecologists who will ensure any adverse impacts on bird or reptile life on the site are minimised.
“We recognise the ecological values of the area and are committed to protecting the native flora and fauna,” says Mr Charles.
The Department of Conservation has granted a concession for use of the reserve for this purpose. Construction will start with securing site access, to be followed by laying the new discharge pipeline network while taking care to avoid harm to existing kānuka trees.
“We expect very little impact on locals and park visitors. There may be a few extra truck movements, but these should not affect the community’s ability to use the Pipeline Track in Poupouwhenua Reserve,” says Mr Charles.
The interim wastewater solution is expected to be fully functional in early 2027 and to remain in place until the new treatment plant and discharge facilities are completed, currently planned for around 2030.