Whangārei Heads Wastewater Scheme

  • Project typeWastewater system improvements
A photo looking out across Parua Bay on a sunny day.

We have several streams of work underway to improve the wastewater scheme at Whangārei Heads.  

Inflow investigations and remediation 

We’re working to reduce stormwater entering the wastewater network in Whangārei Heads. 

When stormwater enters the wastewater system, it can lead to overflows, which have occurred on several occasions at the storage tank on the corner of Richie Road and Whangārei Heads Road in Parua Bay.  

Flow meters across the network show normal volumes during dry weather, however, during heavy rain, flows have risen to more than eight times the average dry-weather level. 

Our investigations aim to identify where stormwater is entering the wastewater system upstream of the storage tank so that they can be remedied.  

Parua Bay pilot study and remediation

We began a pilot study in Parua Bay focusing on the area immediately upstream of the storage tank where the majority of connected Parua Bay properties are located. 

The study was completed in May 2025, revealing issues within the public network as well as on some private properties. 

Smoke testing showed remedial work was required at various manholes on public and private land, including sealing and repairing lids, particularly those located in low-lying areas that are susceptible to flooding.  

Evidence of H2S attack was also found, which is where a build-up of hydrogen sulfide causes corrosion of a manhole’s walls, making them vulnerable to stormwater and groundwater leaking into them. 

Remediation of these issues, which involves sealing all damaged manholes, and using CCTV to check and then repair the pipes feeding into them, was carried out by our stormwater and wastewater maintenance contractor.  

We also engaged with the owners of properties within the pilot study area through surveys and site visits, to explore whether stormwater could be entering gully traps from downpipes, which ultimately feed into the wastewater network. 

While most gully traps on private property were in good condition, there were some that were damaged, incorrectly sealed or set too low, making them susceptible to stormwater inflow.  

Others were located in areas that are prone to flooding and could be overtopped in rainfall events, and some properties also had stormwater being directed into gully traps via downpipes.  

We are following up with these property owners, prioritising issues that will be causing the most inflow in the system.

Find out more about smoke testing:

Smoke testing in our wastewater network 

Further investigations in McGregors Bay, Taurikura Bay and McDonald Road

The Parua Bay system is connected to and therefore impacted by what happens further up the catchment. 

Our monitoring during the Parua Bay pilot study indicated that stormwater was entering the system from the Taurikura Bay and McGregors Bay catchments, so we extended the pilot study to these areas. 

This work follows the same model as the pilot study in Parua Bay, beginning with a questionnaire for residents. 

The questionnaire sought to understand any ponding or flooding related issues that tend to occur during rain events on or around private properties. This helps to highlight any wastewater and stormwater drainage issues, as well as possible fixes. 

Investigations in these areas have been completed, and items of interest are being followed up so that they can be resolved.

Overflow prevention

The volumes flowing into the wastewater system are being monitored 24/7 via flow meters located at several pump stations in the area and level sensors at the Parua Bay pump station storage tank. 

Where our monitoring shows high levels, we are emptying out the storage tank(s) by sucker truck to ensure it doesn’t lead to an overflow.

To help reduce the odour, we have modified the storage tank lids, so they don’t need to be fully opened to do this.  

Network optimisation study

In addition to investigating and remediating stormwater inflow issues in the short term, which will help free up capacity in the system, we are looking at more medium to long-term options to improve the system and increase capacity. 

Our wastewater team is currently carrying out an ‘optimisation study’ to understand how we can speed up wastewater flows from Whangārei Heads into town and assist with capacity. 

Options currently being looked at include modifications to existing pump stations, and introducing new pump stations,  in strategic areas so that wastewater is able to flow more easily. 

We expect to make optimisations of this nature in the short to medium term (one to five years). 

New treatment plant feasibility assessment

We are also in the very early stages of assessing the feasibility of a new treatment plant in the Whangārei Heads area, which would service the wastewater network from Parua Bay to Urquarts Bay. 

This is not included in Council’s current Long Term Plan (to 2035), but will be important to ensure the system can manage projected growth in Whangārei Heads in the future. 

About the Whangārei Heads wastewater system

Wastewater systems are designed to take the wastewater that comes from showers, baths, washing machines, toilets and other household or business sources from the property to a wastewater treatment plant, where it is treated before being disposed of.

In Whangārei Heads, wastewater from household connections flows through wastewater pipes and is pumped to the wastewater treatment plant on Kioreora Road via a series of pump stations. 

The pump stations store wastewater for a while and, when they reach a certain level, the pump sends a manageable amount of wastewater to the next pump station along the pipeline. 

This system depends on every pump along the line working properly, and pumping out at the right time to a storage tank that is empty enough to take the new load.

This cycle works well when wastewater is coming into and being pumped out of the system steadily, but not when there are big fluctuations and very large quantities of wastewater mixed with stormwater coming into the tank very suddenly. When that happens, the tank can be overloaded and there can be an overflow.