Certificate of Compliance
We aim to process your application within 20 working days. If we need further information at any stage during the process we stop the 'processing clock' until you have provided this information.
Subdivision and Land Use consent
We aim to process your application within the following timeframes:
- 20 working days - non-notified applications
- 60 working days - notified applications, if a hearing is not required
- 100 working days - notified applications if a hearing is required.
If you need to provide further information at any stage during the process, the 'processing clock' will stop until you have provided this information.
Setting conditions
During the processing of your resource consent application, we may set conditions on the granting of the consent. Conditions may include:
- undertaking and completing engineering works
- specifying engineering requirements, including plans of the activity
- providing a performance bond
- protecting, restoring and enhancing a natural or physical resource including planting vegetation
- providing an esplanade reserve or strip
- entering into a covenant/consent notice
- measuring and monitoring impacts of the activity.
Find out how to establish a conservation covenant.
Conservation Covenant
Notice of Requirement
We aim to process your application within the following timeframes.
- 20 working days - non-notified applications
- 60 working days - notified applications if a hearing is not required
- 100 working days - notified applications if a hearing is required.
If we need you to provide further information at any stage during the process, the 'processing clock' will stop until you have provided this information.
Land use consent
We will process your application within 20 working days.
If we need you to provide further information at any stage during the process, the 'processing clock' will stop until you have provided this information.
Building consents
Our building officers assess all applications for land use consent. This ensures that if you are applying for a building consent as well as resource consent for your project, the resource consent can be issued first.
In most cases no building work will be allowed to start until the resource consent has been obtained.
Building Consents