Whangārei Heads watermains renewal
- Project typeRenewal
- Project value$2.2M
- Project scheduleNovember 2024 to mid-2025
- Contractor nameNorthern Pipe and Civil Ltd
- Completion Date30 July 2025
We replaced the watermains in Whangārei Heads due to aging and damaged pipes.
The renewals took place in three sections along Whangārei Heads Road:
- Section 1 – from Scott Road to The Pines Golf Club (330m) – completed 6 December 2024
- Section 2 – from Pepi Road to Crisp Road (1.9km) – mid-March to late June 2025
- Section 3 – from Bay View Road to approximately 2288 Whangarei Heads Road (1.4km) – 20 January to mid-April 2025.
During the upgrade, traffic management was in place with stop / go signs and traffic lights where needed.
Residents were notified by council contractors when there will be disruptions to the water supply (expected during the day only).
Section 1 - From Scott Road to The Pines Golf Club (330m)

Section 1 - Scott Road to The Pines Golf Club(PDF, 347KB)
Section 2 - From Pepi Road to Crisp Road (1.9km)

Section 2 - Pepi Road to Crisp Road(PDF, 399KB)
Section 3 - From Bay View Road to approximately 2288 Whangarei Heads Road (1.4km)

Section 3 - Bay View Road to 2288 Whangarei Heads Road(PDF, 349KB)