Te Kamo carpark resurfacing and pedestrian improvements

  • Project typeTransport
  • Project value$300,000
  • Project scheduleMarch to May 2026
  • Contractor nameVentia
Map showing the area in scope for the Te Kamo carpark resurfacing and pedestrian improvements.

The Te Kamo village carpark is frequently used by the local public due to its proximity to several businesses, schools and nearby daycare centres. 

Te Kamo Community Inc representatives have highlighted that pedestrian safety in this space is at high risk, particularly for schoolchildren and families who use the area.

The Te Kamo village carpark is scheduled for resurfacing as part of renewal works to repair existing pavement damage. 

Alongside these works, improvements will also be made to enhance pedestrian safety and the organisation of parking spaces.

The scope of the project will include:

  • creating safe pedestrian routes to connect areas with high foot traffic
  • re-marking and reconfiguring parking spaces to improve consistency
  • refurbishing or removing gardens, bins, signs and bollards
  • removing unsafe / unhealthy trees or trees that are damaging the carpark and pipes (new trees will be planted)
  • asphalt resurfacing.

Due to the tight site constraints, ensuring safety for road users and workers, along with a desire to have the works completed as soon as possible (prior to winter), sections of the carpark may be temporarily closed at various times.

Asphalt work 

Asphalt work is planned from Monday 4 to Friday 8 May 2026, weather permitting. 

The carpark area will be asphalted in stages to help reduce disruption (see image and schedule below).

Because some areas are very busy and to keep everyone safe, the main carpark (Zone 2) will need to be fully closed during construction.

No parking will be available for up to three days in total. Limited access may still be available at times, depending on the work happening that day. The schedule is outlined below. 

Work schedule: 

  • Zone 3 closed – Monday 4 May 2026, 7:00am to 6:00pm (day works)
  • Zone 2 closed – Monday 4 to Wednesday 6 May 2026, 7:00am to 6:00pm (day works)
  • Zones 1 and 4 closed – Thursday 7 May 2026, 9:00am to 3:00pm (day works)
  • Zone 5 closed – Thursday 7 May 2026 (night works).
Map showing zones of closure of Te Kamo carpark for asphalt work.

Access to local businesses will be maintained at all times.

We appreciate your patience and understanding while these improvements are completed.

Location

McDonald's Kamo, Te Kamo 0112  View Map

Google Map