Semenoff Stadium roof replacement

  • Project typeRoof replacement
  • Project value$7.5 million
  • Project scheduleMay 2026 to June 2027
  • Contractor nameArgon
Architect's concept render of the new stadium roof exterior canopy.

Project overview

Semenoff Stadium's ageing roof is being replaced, ensuring the venue remains fit for purpose and able to host high-quality events year-round.

The existing canopy roof has reached the end of its design life and is no longer performing as required. It presents ongoing challenges including weather-tightness issues, increasing maintenance costs, and inefficiencies in heating and moisture control.

The project will replace the current roof with a modern long-span structure designed to improve durability, performance and overall user experience.

What the project includes

In addition to the roof replacement, upgrades will include:

  • building services
  • lighting systems
  • acoustics
  • air conditioning and indoor environmental quality
  • cultural design elements reflecting the identity of the region.

Benefits

The upgrade will:

  • improve comfort and functionality for users
  • enhance the visitor and event experience
  • improve energy efficiency and building performance
  • reduce ongoing maintenance requirements
  • support increased use of the venue.

Community and economic impact

The project represents a significant investment in one of Northland’s premier sporting and events facilities and will help position the venue to better support future sporting, entertainment, business and community events.  

The construction contract has been awarded to Argon, with work expected to provide opportunities for local contractors and suppliers.

Images are architect's concept renders of the new Semenoff Stadium roof. 

Location

Semenoff Stadium, 51 Okara Drive, Whangārei 0148  View Map

Google Map