Roadworks begin on Mill Road

 
This page contains a news story about maintenance and improvements to Mill Road.
Updated: 12/03/2020 9:32 a.m.

​Council is starting the first stage of a $2million roading project this week on Mill Road.

The project will start with kerb, channel, and drainage improvements as well as new footpaths, on the section of Mill Road between Brighton Road and Whareora Road. 

Stylised map of the Mill Road project stages. This is expected to take three months and once complete work will begin on the section of Mill Road between Nixon Street and the Bank Street/Manse Street intersection.

Traffic will still be able to travel in both directions during the road works, however there will still be some delays as traffic management and a 30km speed limit will be in place. 

Drivers should consider using alternative routes or allow for extra time to complete their journey. 

“Some service relocations and road crossings will be done at night to minimise disruption to drivers but the majority of the work needs to be done in daylight because of its complexity and the close proximity of residents to the road,” says Whangarei District Council Capital Works and Procurement Manager Greg Monteith.

“The Mill Road roading project is a significant investment on one of the main arterial routes into the city. We are also taking the opportunity to renew old infrastructure, future proofing the road, ready to serve us well for the next 25 years,” says Mr Monteith.

Mr Monteith says rebuilding and resealing the road is scheduled for the later part of the year.

 

Stage 1 – Kerb, channel and footpath replacement and drainage improvements between Brighton Road and Whareora Road. The work is expected to take three months to complete. March through to June.

Stage 2 - Kerb, channel and footpath replacement and drainage improvements between Mill Road/Nixon Street intersection and Bank Street/Manse Street intersection. The work is expected to take two months to complete. June through to August 

Stage 3 – Rebuilding and sealing of the road between Brighton Road and Whareora Road. This work is expected to take around six weeks to complete. September and October. 

Stage 4 – Rebuilding and sealing of the road between Mill Road/Nixon Street intersection and Bank Street/Manse Street intersection. This work is expected to take around seven weeks to complete during October and November. 

 

 

Resources

Disclaimer/Copyright

Whangarei District Council owns this website and the information, images and photographs in it are subject to copyright. No portion may be copied or republished without prior permission of Whangarei District Council. We have made every reasonable effort to provide accurate and reliable information. The use of any information is at the website visitor’s own risk and discretion.